Timeline of key events related to the Subansiri Lower Hydroelectric Project.
2003
Project approved initially
2011
Construction halted due to environmental concerns and protests
2019
Construction resumed after clearances
2020
Environment Ministry issued first reminder on compensatory afforestation
2026
Compensatory afforestation plans under review by MoEFCC; avulsion hydro-peaking decision
Connected to current news
Subansiri Hydel Project: Key Aspects
Mind map illustrating the key aspects of the Subansiri Hydel Project, including its objectives, environmental concerns, and legal framework.
1 minOther
Subansiri Hydel Project Timeline
Timeline of key events related to the Subansiri Lower Hydroelectric Project.
2003
Project approved initially
2011
Construction halted due to environmental concerns and protests
2019
Construction resumed after clearances
2020
Environment Ministry issued first reminder on compensatory afforestation
2026
Compensatory afforestation plans under review by MoEFCC; avulsion hydro-peaking decision
Connected to current news
Subansiri Hydel Project: Key Aspects
Mind map illustrating the key aspects of the Subansiri Hydel Project, including its objectives, environmental concerns, and legal framework.
Subansiri Hydel Project
2,000 MW Power Generation
Compensatory Afforestation
Downstream Impacts
EIA Notification 2006
NHPC
Connections
Objectives→Environmental Concerns
Environmental Concerns→Legal Framework
Subansiri Hydel Project
2,000 MW Power Generation
Compensatory Afforestation
Downstream Impacts
EIA Notification 2006
NHPC
Connections
Objectives→Environmental Concerns
Environmental Concerns→Legal Framework
Other
सुबनसिरी जलविद्युत परियोजना
सुबनसिरी जलविद्युत परियोजना क्या है?
सुबनसिरी लोअर हाइड्रोइलेक्ट्रिक प्रोजेक्ट सुबनसिरी नदी पर बन रहा एक बड़ा बांध है ब्रह्मपुत्र नदी की एक सहायक नदी। इसका लक्ष्य 2,000 मेगावाट पनबिजली पैदा करना है।
ऐतिहासिक पृष्ठभूमि
यह परियोजना पहली बार 2003 में स्वीकृत हुई थी, लेकिन पर्यावरणीय चिंताओं और स्थानीय विरोधों के कारण इसमें काफी देरी हुई। निर्माण 2011 में रोक दिया गया और मंजूरी के बाद 2019 में फिर से शुरू हुआ।
मुख्य प्रावधान
10 points
1.
अरुणाचल प्रदेश और असम की सीमा पर स्थित है।
2.
2,000 मेगावाट पनबिजली पैदा करने का लक्ष्य है।
3.
एक बड़े कंक्रीट गुरुत्वाकर्षण बांध का निर्माण शामिल है।
4.
परियोजना डेवलपर नेशनल हाइड्रोइलेक्ट्रिक पावर कॉर्पोरेशन (NHPC) है।
5.
दृश्य सामग्री
Subansiri Hydel Project Timeline
Timeline of key events related to the Subansiri Lower Hydroelectric Project.
पर्यावरणीय चिंताओं और स्थानीय विरोध के कारण सुबनसिरी परियोजना को कई बाधाओं का सामना करना पड़ा है, जिससे काफी देरी हुई है।
2003परियोजना को शुरू में मंजूरी दी गई
2011पर्यावरणीय चिंताओं और विरोधों के कारण निर्माण रोका गया
2019स्वीकृति के बाद निर्माण फिर से शुरू हुआ
2020पर्यावरण मंत्रालय ने क्षतिपूरक वनीकरण पर पहला रिमाइंडर जारी किया
2026MoEFCC द्वारा क्षतिपूरक वनीकरण योजनाओं की समीक्षा; अवल्शन हाइड्रो-पीकिंग निर्णय
Subansiri Hydel Project: Key Aspects
Mind map illustrating the key aspects of the Subansiri Hydel Project, including its objectives, environmental concerns, and legal framework.
UPSC GS Paper 1 (भूगोल - नदी प्रणाली), GS Paper 3 (पर्यावरण और बुनियादी ढांचा) के लिए महत्वपूर्ण। नदी परियोजनाओं, पर्यावरण प्रभाव आकलन और संबंधित नीतियों के बारे में प्रश्न पूछे जा सकते हैं।
❓
सामान्य प्रश्न
6
1. What is the Subansiri Lower Hydroelectric Project and what is its primary objective?
The Subansiri Lower Hydroelectric Project is a major gravity dam project under construction on the Subansiri River, a tributary of the Brahmaputra. Its primary objective is to generate 2,000 MW of hydroelectric power.
परीक्षा युक्ति
Remember the river name (Subansiri) and the power generation target (2,000 MW) for prelims.
2. What are the key provisions of the Subansiri Lower Hydroelectric Project?
The key provisions of the Subansiri Lower Hydroelectric Project include:
•Location on the border of Arunachal Pradesh and Assam.
•Aim to generate 2,000 MW of hydroelectric power.
•
Other
सुबनसिरी जलविद्युत परियोजना
सुबनसिरी जलविद्युत परियोजना क्या है?
सुबनसिरी लोअर हाइड्रोइलेक्ट्रिक प्रोजेक्ट सुबनसिरी नदी पर बन रहा एक बड़ा बांध है ब्रह्मपुत्र नदी की एक सहायक नदी। इसका लक्ष्य 2,000 मेगावाट पनबिजली पैदा करना है।
ऐतिहासिक पृष्ठभूमि
यह परियोजना पहली बार 2003 में स्वीकृत हुई थी, लेकिन पर्यावरणीय चिंताओं और स्थानीय विरोधों के कारण इसमें काफी देरी हुई। निर्माण 2011 में रोक दिया गया और मंजूरी के बाद 2019 में फिर से शुरू हुआ।
मुख्य प्रावधान
10 points
1.
अरुणाचल प्रदेश और असम की सीमा पर स्थित है।
2.
2,000 मेगावाट पनबिजली पैदा करने का लक्ष्य है।
3.
एक बड़े कंक्रीट गुरुत्वाकर्षण बांध का निर्माण शामिल है।
4.
परियोजना डेवलपर नेशनल हाइड्रोइलेक्ट्रिक पावर कॉर्पोरेशन (NHPC) है।
5.
दृश्य सामग्री
Subansiri Hydel Project Timeline
Timeline of key events related to the Subansiri Lower Hydroelectric Project.
पर्यावरणीय चिंताओं और स्थानीय विरोध के कारण सुबनसिरी परियोजना को कई बाधाओं का सामना करना पड़ा है, जिससे काफी देरी हुई है।
2003परियोजना को शुरू में मंजूरी दी गई
2011पर्यावरणीय चिंताओं और विरोधों के कारण निर्माण रोका गया
2019स्वीकृति के बाद निर्माण फिर से शुरू हुआ
2020पर्यावरण मंत्रालय ने क्षतिपूरक वनीकरण पर पहला रिमाइंडर जारी किया
2026MoEFCC द्वारा क्षतिपूरक वनीकरण योजनाओं की समीक्षा; अवल्शन हाइड्रो-पीकिंग निर्णय
Subansiri Hydel Project: Key Aspects
Mind map illustrating the key aspects of the Subansiri Hydel Project, including its objectives, environmental concerns, and legal framework.
UPSC GS Paper 1 (भूगोल - नदी प्रणाली), GS Paper 3 (पर्यावरण और बुनियादी ढांचा) के लिए महत्वपूर्ण। नदी परियोजनाओं, पर्यावरण प्रभाव आकलन और संबंधित नीतियों के बारे में प्रश्न पूछे जा सकते हैं।
❓
सामान्य प्रश्न
6
1. What is the Subansiri Lower Hydroelectric Project and what is its primary objective?
The Subansiri Lower Hydroelectric Project is a major gravity dam project under construction on the Subansiri River, a tributary of the Brahmaputra. Its primary objective is to generate 2,000 MW of hydroelectric power.
परीक्षा युक्ति
Remember the river name (Subansiri) and the power generation target (2,000 MW) for prelims.
2. What are the key provisions of the Subansiri Lower Hydroelectric Project?
The key provisions of the Subansiri Lower Hydroelectric Project include:
•Location on the border of Arunachal Pradesh and Assam.
•Aim to generate 2,000 MW of hydroelectric power.
•
नदी के पारिस्थितिकी तंत्र और स्थानीय समुदायों पर डाउनस्ट्रीम प्रभावों के बारे में चिंताएं।
6.
पर्यावरणीय क्षति को कम करने के लिए मुआवजे वनीकरण की आवश्यकता है।
7.
जटिल पर्यावरण प्रभाव आकलन (ईआईए) शामिल है।
8.
क्षेत्र में भूकंपीय गतिविधि के बारे में चिंताएं।
9.
हाथी को नदी पार करने देने के लिए अवल्शन हाइड्रो-पीकिंग।
10.
क्षेत्र में बुनियादी ढांचे के विकास में महत्वपूर्ण निवेश।
●Legal Framework
●Stakeholders
Construction of a large concrete gravity dam.
•Project developer is National Hydroelectric Power Corporation (NHPC).
•Concerns regarding downstream impacts on river ecology and local communities.
परीक्षा युक्ति
Focus on the location, power generation capacity, and implementing agency (NHPC).
3. What environmental and social concerns are associated with the Subansiri Lower Hydroelectric Project?
The project faces concerns regarding downstream impacts on river ecology and local communities. These concerns led to project delays and construction halts.
परीक्षा युक्ति
Understand the potential negative impacts of large dam projects on river ecosystems and local populations.
4. What is the legal framework governing the Subansiri Lower Hydroelectric Project?
•Guidelines from the Ministry of Environment, Forest and Climate Change (MoEFCC)
परीक्षा युक्ति
Remember the key environmental laws and the role of MoEFCC.
5. What are the challenges in the implementation of the Subansiri Lower Hydroelectric Project?
Challenges include environmental concerns, local protests, and the need for clearances. Mitigating downstream impacts and ensuring safety are also key challenges.
परीक्षा युक्ति
Consider the socio-economic and environmental trade-offs involved in such large infrastructure projects.
6. What is the significance of the Subansiri Lower Hydroelectric Project for India's energy security?
The project aims to generate 2,000 MW of hydroelectric power, which can contribute to India's energy security by increasing the availability of renewable energy.
परीक्षा युक्ति
Relate the project to India's broader goals of increasing renewable energy capacity and reducing carbon emissions.
नदी के पारिस्थितिकी तंत्र और स्थानीय समुदायों पर डाउनस्ट्रीम प्रभावों के बारे में चिंताएं।
6.
पर्यावरणीय क्षति को कम करने के लिए मुआवजे वनीकरण की आवश्यकता है।
7.
जटिल पर्यावरण प्रभाव आकलन (ईआईए) शामिल है।
8.
क्षेत्र में भूकंपीय गतिविधि के बारे में चिंताएं।
9.
हाथी को नदी पार करने देने के लिए अवल्शन हाइड्रो-पीकिंग।
10.
क्षेत्र में बुनियादी ढांचे के विकास में महत्वपूर्ण निवेश।
●Legal Framework
●Stakeholders
Construction of a large concrete gravity dam.
•Project developer is National Hydroelectric Power Corporation (NHPC).
•Concerns regarding downstream impacts on river ecology and local communities.
परीक्षा युक्ति
Focus on the location, power generation capacity, and implementing agency (NHPC).
3. What environmental and social concerns are associated with the Subansiri Lower Hydroelectric Project?
The project faces concerns regarding downstream impacts on river ecology and local communities. These concerns led to project delays and construction halts.
परीक्षा युक्ति
Understand the potential negative impacts of large dam projects on river ecosystems and local populations.
4. What is the legal framework governing the Subansiri Lower Hydroelectric Project?
•Guidelines from the Ministry of Environment, Forest and Climate Change (MoEFCC)
परीक्षा युक्ति
Remember the key environmental laws and the role of MoEFCC.
5. What are the challenges in the implementation of the Subansiri Lower Hydroelectric Project?
Challenges include environmental concerns, local protests, and the need for clearances. Mitigating downstream impacts and ensuring safety are also key challenges.
परीक्षा युक्ति
Consider the socio-economic and environmental trade-offs involved in such large infrastructure projects.
6. What is the significance of the Subansiri Lower Hydroelectric Project for India's energy security?
The project aims to generate 2,000 MW of hydroelectric power, which can contribute to India's energy security by increasing the availability of renewable energy.
परीक्षा युक्ति
Relate the project to India's broader goals of increasing renewable energy capacity and reducing carbon emissions.